The Status Entrance Date report shows the date an issue has moved to a particular status.

  1. Choose the Status Entrance Date report;

2. Filter by the category you need;

3. Choose thedate ranges for the data calculation;

  1. Choose the issue range for the data calculation;

5. Get dates when the issue has entered each of the statuses on the grid as it’s shown below.

On the chart, it shows the number of tasks that have entered a status on a certain date - for example, 1 task out of 5 tasks has entered the Progress status for the first time on the 23-rd of May.

Panel
panelIconId1f468-1f3fb-200d-1f4bb
panelIcon:man_technologist::skin-tone-2:
panelIconText👨🏻‍💻
bgColor#F4F5F7

Request a demo call

Info

If you need help or want to ask questions, please contact SaaSJet Support or email us at support@saasjet.atlassian.net

Tip

Haven’t worked with the add-on yet? Give it a try

https://marketplace.atlassian.com/apps/1219732/?tab=overview&utm_campaign=Time%20in%20status%20per%20assignee&utm_medium=documentation&utm_source=Confluence&hosting=cloud