The Time in Status per Date report sums up the time the task has been staying in each status at a particular date.
Choose the Time in Status per Date report;
2. Filter by the category you need;
3. Choose the date ranges for the data calculation;
4. Choose the issue range for the data calculation;
5. Choose a time format type that will be represented on the grid;
6. Get the transition count data on the grid as it’s shown below.
Time in status per Date counts the total time the sample tasks have spent in statuses.
For example - on the 24th of May, 3 tasks out of 6 were in To-Do status for 2, 3, and 1 hours. So for the To-Do status on the 24th of May, the time in the status is 2 + 3 + 1 = 6 hours
(for the graph and the grid the calculation process is the same)