The Time in State report shows the total time a Work Item has stayed in each status.

  1. Choose the Time in State report.

Знімок екрана 2024-06-17 о 00.12.31.png
  1. Filter by the Query you need.

Знімок екрана 2024-06-17 о 00.13.02.png
  1. Choose the date ranges for the data calculation.

Знімок екрана 2024-06-16 о 22.17.51-20240616-191757.png
  1. Choose the time format type that will be represented on the grid.

Знімок екрана 2024-06-16 о 22.19.08-20240616-191913.png
  1. Get all the data on the grid as it’s shown below.

The time in state data that is displayed on the grid calculates in such a way: 

For example, the Work Item was in the Proposed state for 1h 21m , then moved to the Active state. After a while, the Work Item returned to the Proposed state and stayed there for 1 hour until it moved to another state. So the time in the Proposed state for this Work Item is 2h 21m.

Знімок екрана 2024-06-16 о 22.27.32.png

The report calculation in the Charts view occurs during the chosen period. It counts the total time of the sample Work Item in states.

Don't forget that you can export reports in .xlsx and .csv formats.

Знімок екрана 2024-06-17 о 00.13.59-20240616-211406.png

If you need help or want to ask questions, please contact SaaSJet Support or email us at support@saasjet.atlassian.net